On the same day in May 2019, the Army Corps of Engineers awarded a pair of contracts worth $788 million to replace 83 miles of fence along the southwest border.
The
projects were slated to be completed in January 2020, the Corps said then. Four months into this year, however, the government increased the value of the contracts by more than $1 billion, without the benefit of competitive bidding designed to keep costs low to taxpayers.
Within a year of the initial award, the value of the two contracts had more than tripled, to over $3 billion, even though the length of the fence the companies were building had only grown by 62%, to 135 miles. The money is coming from military counter-narcotics funding.
Those contract spikes were dramatic, but not isolated. A review of federal spending data shows more than 200 contract modifications, at times awarded within just weeks or months after the original contracts, have increased the cost of the border wall project by billions of dollars since late 2017. This is particularly true this year, in the run-up to next week’s election. The cost of supplemental agreements and change orders alone — at least $2.9 billion — represents about a quarter of all the money awarded and more than what Congress originally appropriated for wall construction in each of the last three years.